Introducing our new photovoltaic plant in Argentina. Awarded through the Renovar Mini Round 3 Programme, it will be our first project in the country.
We continue our expansion with the San Martín Project. After more than a decade of activity on the American continent, this solar project is our new photovoltaic plant in Argentina.
At the end of 2019, through the Renovar Mini Round 3 Programme, Enerland was awarded this project. Following this, at the beginning of 2020, the contract was signed under the PPA or Power Purchase Agreement model. Through this type of agreement, one party generates the electricity while the other undertakes to purchase the electricity produced over a defined period of time. On this occasion, the agreed term exceeds 20 years.
On a site of more than 24 hectares in the province of Mendoza, the San Martín solar plant will generate a peak power output of 13.6 MWp. It will also feature a single-axis tracker structure and 540W modules.
In line with the project timeline, it is currently in the development phase. As for commissioning, this is expected to take place by the end of 2022.
Enerland in America
With this new project in Argentina, Enerland now has 15 projects in the Americas. Since we announced our commitment to the continent more than a decade ago, we have continued to grow. We currently have more than 318,600 MWh of energy produced in the Americas and expect to keep increasing our figures.
Solar photovoltaic energy is a clear choice. The development of this type of renewable energy not only makes electricity more accessible but also more affordable. In a world that is increasingly globalised and dependent on technology, it is ever more necessary to meet the growing demand for electricity through energy derived from non-polluting sources.
Update 12/11/2021
Through Resolution 1090/2021 of the Secretariat of Energy, the San Martín solar park has been authorised to enter the electricity market.
On 12 November 2021, Enerland Group Argentina obtained authorisation for the connection point to enter the Argentine electricity market. In 2019, it was confirmed that the San Martín solar park met all the required conditions. Once built, the Enerland San Martín Solar Photovoltaic Park will be able to add to the electricity system 10 MW from the energy generated by its panels by connecting to the transformer substation at Edeste S.A.